Get the latest update CompTIA Project+ exam dumps to pass the exam

CompTIA Project+ exam “PK0-004”. The latest updated PK0-004 exam dumps with PDF and VCE to help you successfully pass the exam.

The CompTIA Project+ article is an advanced exam content temporarily released. Get more free CompTIA Project+ exam series from BrainDump4it share.

Of course, you can also get the complete exam dumps directly in Lead4Pass CompTIA Project+.
The PK0-004 exam is part of the CompTIA Project+ exam series. The complete PK0-004 exam dumps: https://www.lead4pass.com/pk0-004.html (PDF+VCE)

You can first take part in the pk0-004 exam practice test on this site to test your ability.

The latest CompTIA PK0-004 practice test questions

Are you ready? The small hint test answer is at the end of the article.

QUESTION 1

An active project is focused on quality assurance of the deliverable product. In which of the following project phases
would this occur?

A. Execution
B. Monitor and control
C. Planning
D. Closing

QUESTION 2

Project B cannot start before Project A is complete, but Project B has been given the authorization to begin to meet
legislative requirements.
Which of the following is the BEST way to expedite the projects?

A. Project A can reduce the number of deliverables.
B. Project A can be crashed using Project B\’s resources.
C. Project B can have its resources leveled.
D. Project B can begin without Project A completing, therefore accepting future rework.

QUESTION 3

A project is in the initiation phase. Which of the following tasks will take place during this phase?

A. Develop a WBS.
B. Define the project requirements.
C. Create a project charter.
D. Acquire the project resources.

QUESTION 4

Many questions have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver. Which of the following would be the BEST way to provide this
information?

A. Kickoff meeting
B. Status report
C. Company-wide email
D. CCB meeting

QUESTION 5

A project manager creates a Pareto chart based on the table below:

comptia pk0-004 exam questions q5

Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and
faulty installation?

A. To take preventive action and identify the causes resulting in the highest number of issues
B. To take corrective action and identify the effects resulting in the highest number of issues
C. To take preventive action and identify and frequencies resulting in the highest number of issues
D. To take corrective action and identify the causes resulting in the highest number of issues

QUESTION 6

A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager to use FIRST to relay this information?

A. Individually call all project team members.
B. Send an email to all project team members.
C. Schedule a conference call.
D. Schedule a face-to-face meeting.

QUESTION 7

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

A. SOW
B. PO
C. SLA
D. MOU

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299

QUESTION 8

In which of the following circumstances would faxing be the MOST appropriate communication method?

A. When sending confidential information
B. When resolving complex issues
C. When providing weekly status updates
D. When signatures are required

QUESTION 9

Which of the following will identify the MOST potential project risks?

A. Cost-benefit analysis
B. Past project documentation
C. Project budget
D. Benchmarking

QUESTION 10

A risk with a minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

A. internal project team.
B. key stakeholders.
C. affected team members.
D. full project team.

QUESTION 11

A project sponsor informs the project manager that the project completion date must be moved one month earlier.
Which of the following should the project manager do NEXT?

A. Recalculate the critical path, determine the new cost, schedule baselines, and initiate the change request process.
B. Recalculate the schedule and cost variance and report the changes to the project stakeholders and sponsor.
C. Calculate the cost of crashing the schedule and obtain the stakeholders\’ approval for the new project WBS and
timeline.
D. Calculate the additional resource requirements that are necessary to meet the new project deadline and work with
human resources to hire additional staff.

QUESTION 12

New requirements were introduced during the execution phase of a project, and the team believes this will impact the
project cost but not the timely completion of project deliverables.
Which of the following is the BEST way for the PM to validate the assessment?

A. Ask the team for estimates and review the project schedule and budget.
B. Ask the team to review the product scope and validate its impact on the schedule and quality.
C. Ask the team for estimates and review the cost management plan.
D. Ask the team to perform a SWOT analysis and validate the assessment.

QUESTION 13

A project manager recently joined a projectized organization and is having many issues on five different projects. Which of the following risk activities should be performed FIRST? (Choose two.)

A. Identify
B. Coordinate
C. Qualify
D. Brainstorm
E. Mitigate
F. Assign

Publish the answer:

Q1Q2Q3Q4Q5Q6Q7Q8Q9Q10Q11Q12Q13
BBCAACADBBBDAB

CompTIA PK0-004 Exam PDF is hosted on Google Drive

In order to facilitate the study habits of more people, this site continues to share the CompTIA PK0-004 exam PDF.
You can download it for free and watch it at any time.

Finally: Thank you for watching! This article is sponsored by Lead4Pass. All PK0-004 exam dumps are the latest updates, we update throughout the year, and update the exam content immediately. This is not to help you understand every question in the book, here to help you pass the exam! Remind again the complete CompTIA Project+ PK0-004 exam dumps: https://www.lead4pass.com/pk0-004.html (Total Questions: 653 Q&A)